Size | Medium | ||||||||
---|---|---|---|---|---|---|---|---|---|
Budget Epic Name | CDP-178 Moodle 4.0 | ||||||||
Jira Outcome |
|
| ||
Feature Lead |
---|
TI3 Deliverables:
...
What: Update the UCL Moodle Staff and Student Wiki to reflect any changes caused by the move to Moodle 4.2. Identify any other connected resources that may require updating.
...
Why: ???.
Nikola Bozhkov |
Outcome Description:
FOR WHO: Staff, students all stakeholders of DLE systems/platforms and integrations
WHAT: Providing support, maintenance, development and testing of the DLE platforms, in partnership with hosting partners, 3rd party product vendors across both product software, infrastructure and DEV/OPS implementations.
WHY (Business Value): Ensuring business continuity, security of service, scalability and performance for core systems
Dependencies
Catalyst IT, Internal product resources, specialist skill sets as required
Risks:
Lack of internal resource
Outcome Deliverables EPICs:
TI3
...
Load testing preparation (spike) - https://ucldata.atlassian.net/browse/CTP-2656
What: Vendor discussions and spike
Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).
Dependency: ? / Risk: ?
Create and deliver staff training on the new version of Moodle 4.2 - CTP-1988: Create and deliver staff training on the new version of Moodle 4.2
What: To deliver the change from Moodle 3.11 to Moodle 4.2 this summer, the VLE team need to provide training materials in several areas for Teaching Staff and Administrative staff. Since the VLE team does not have the resources to implement this fully, the team will be working with external partners to produce the materials and with a feature lead/coordinator to ensure that training is delivered on time. The approach we will be taking is to construct a core training package for staff on the new and changed features between 3.11 and 4.0/4.1/4.2. We will create a train-the-trainer programme so that FLTL's, departmental learning technologists and others can be trained in the changes and the materials so that they can deliver the training in their departments/faculties.
Why: ???What: Vendor discussions and spike
Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).
Dependency: ? / Risk: ?
Load testing preparation (spike) - https://ucldata.atlassian.net/browse/CTP-2656
What: Vendor discussions and spike
Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).
Dependency: ? / Risk: ?
Load testing preparation (spike) - https://ucldata.atlassian.net/browse/CTP-2656
Create and deliver student guidance on the new version of Moodle 4.2 - CTP-1989: Create and deliver student guidance on the new version of Moodle 4.2
What: The approach we will be taking is to update the student wiki guides, provide a how-to-navigate Moodle video and provide a Moodle User Journey for students.
Why: To deliver the change from Moodle 3.11 to Moodle 4.2 this summer, the VLE team need to provide training materials in several areas for Students.
Dependency: ???.
Moodle 4.x training, Planning and Development - CTP-1761: Moodle 4.x training, Planning and Development
What: The approach we will be taking is to construct a core training package for staff on the new and changed features between 3.11 and 4.0/4.1/4.2. We will create a train-the-trainer programme so that FLTL's, departmental learning technologists and others can be trained in the changes and the materials so that they can deliver the training in their departments/faculties
Why: To deliver the change from Moodle 3.11 to Moodle 4.2 this summer, the VLE team need to provide training materials in several areas for Students, Teaching Staff, and Administrative staff. Since the VLE team does not have the resources to implement this fully, the team will be working with external partners to produce the materials and with a feature lead/coordinator to ensure that training is delivered on time.
Dependency: ???.
Moodle 4.2 Accessibility review - CTP-1986: Moodle 4.2 Accessibility review
- What: Conduct reviews into various accessibility elements in association with the Head of Digital Accessibility. Create a generic Moodle 4.2 accessibility statement that could be used by other institutions. Create a UCL specific accessibility statement as a separate section. Work with Titus, Catalyst and internal teams to resolve any accessibility issues identified.
- Why: The move to Moodle 4.2 requires us to rewrite the Moodle accessibility statement. This will be done in conjunction with Ben Watson Head of Digital Accessibility.
Load testing preparation (spike) - https://ucldata.atlassian.net/browse/CTP-2656
What: Vendor discussions and spike
Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).
Dependency: ? / Risk: ?
Load testing preparation (spike) - https://ucldata.atlassian.net/browse/CTP-2656
What: Vendor discussions and spike
Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).
Dependency: ? / Risk: ?
Preview Improvements for Moodle 4 - CTP-2021
What: ??
Why: In TI2, the Preview environment was implemented in AWS and pipeline migrated to Github Actions. We now need to keep improving this environment to support it's availability to demo Moodle 4.
Dependency: ? / Risk: ?
DLE Operations - CTP-392
What: FR, CIs, Moodle releases, Monthly Manual patching, Service Health Reviews - Schedule & docs, etc.
Why: Day-to-day operational support and monitoring are essential to maintain a complex system such as Moodle and ensure value for stakeholders.
Dependency: Catalyst/Vendor resource / Risk: The product requires an additional member of staff within this team area to support our services.