Budget Epic Name

CDP-178 Moodle 4.0

Jira Epic

Jira Legacy
serverJIRA
serverId96b2214f-2cdb-3608-8462-892f17ad04be
keyCTP-2349

Feature Lead

Jason Norton / Eliot Hoving

...


TI3 Deliverables:

  • Load testing preparation (spike) - Image AddedCTP-2656: TI1 23-24 - Load testing preparation (spike)DONE

    • What: Vendor discussions and spike

    • Why: It is critical that we have robust solutions to measure and ensure that UCL systems are provisioned correctly and can respond to increases in load. We also require a solution that can be replicated and used to benchmark our solution and to measure against specific scenarios (eg assessment load).

    • Dependency: ? / Risk: ?

  • Moodle Upgrade 4.3 + Associated work - Image AddedCTP-2655: TI1 23-24 - Moodle upgrade 4.3IN PROGRESS

    • What: Codebase and testing / Upskill Nikola and Matthis on upgrade/deployment

    • Why: Moodle is UCL’s core teaching and learning platform. We need to ensure that the platform is maintained and upgraded to ensure that it continues to offer the best experience to our stakeholders. Upgrading the platform ensures we have the latest features and fixes in place. Moodle 4.3 specifically has large scale performance enhancements and additons to the quiz feature.

    • Dependency: ? / Risk: ?

  • DLE Operations - Image AddedCTP-2654: TI1 23-24 DLE OperationsIN PROGRESS

    • What: FR, CIs, etc.

    • Why: Day to day operational support and monitoring is essential to maintain a complex system such as Moodle and ensure value for stakeholders.

    • Dependency: Catalyst/Vendor resource / Risk: The product requires an additional member of staff within this team area to support our services.